Analisis Risiko Pada Proyek Konstruksi

Julianda Astari Kawulusan, Ariestides K. T. Dundu, Audie L. E. Rumayar

Abstract


Abstract: The method used in this study for risk analysis is the Severity Index (SI) method combined with probability and impact matrix and uses risk acceptability analysis. The results show that the dominant risk (major risk) to time there are 10 risks consisting of 3 risk variables the Unacceptable category (unacceptable) (9.09%) and 7 risk variables  the Undesirable category (undesirable) (21.21%) with various sources of risk, namely: contract, material, design, and environment. Meanwhile, the dominant risk (major risk) to costs, there are 6 risks consisting of 6 risk variables the Undesirable (undesirable) category (18.18%) with various risk sources, namely: contracts and designs. The most dominant risk response (major risk) against time in the Unacceptable category (unacceptable) carried out 3 risk response actions and in the Undesirable category (undesirable) carried out 7 risk response actions were with a handling strategy, namely reducing risk. The most dominant risk response (major risk) to costs in the Undesirable category (undesirable) is carried out 6 risk response actions with a handling strategy, namely reducing risk.

 

Abstrak: Metode yang digunakan pada penelitian ini untuk analisis risiko yaitu metode Severity Index (SI) yang dikombinasikan dengan matriks probababilitas (probability) dan dampak (impact) serta menggunakan analisis tingkat penerimaan risiko (risk acceptability). Hasil penelitian menampilkan bahwa Risiko yang dominan (major risk) terhadap waktu terdapat 10 risiko yang terdiri dari 3 variabel risiko kategori Unacceptable (tidak dapat diterima) (9,09%) dan 7 variabel risiko kategori Undesirable (tidak diharapkan) (21,21%) dengan berbagai sumber risiko yaitu : kontrak, material, desain, dan lingkungan. Sedangkan, risiko yang dominan (major risk) terhadap biaya terdapat 6 risiko yang terdiri dari 6 variabel risiko kategori Undesirable (tidak diharapkan) (18,18%) dengan berbagai sumber risiko yaitu : kontrak dan desain. Respon risiko yang paling dominan (major risk) terhadap waktu pada kategori Unacceptable (tidak dapat diterima) dilakukan 3 tindakan respon risiko dan pada kategori Undesirable (tidak diharapkan) dilakukan 7 tindakan respon risiko dengan strategi penanganan yaitu mengurangi risiko. Respon risiko yang paling dominan (major risk) terhadap biaya dengan kategori Undesirable (tidak diharapkan) dilakukan 6 tindakan respon risiko dengan strategi penanganan yaitu mengurangi risiko.


Keywords


Risk Analysis ; Severity Index (SI) ; Risk Matrix ; Risk Acceptability . Kata kunci : Analisis Risiko ; Severity Index (SI) ; Matriks Risiko ; Penerimaan Risiko

References


Arikunto, Suharsimi. (2002). Prosedur Penelitian Suatu pendekatan Praktek, Edisi Revisi V, Jakarta, PT. Rineka Cipta.

Dewi, A.I., Nurcahyo, C.B. (2013). Analisis Risiko pada Proyek Pembangunan Underpass di Simpang Dewa Ruci Kuta Bali, Jurnal Teknik Pomits Vol.2, No.2, (2013) ISSN: 2337-3539 (2301-9271), Jurusan Teknik Sipil, FTSP, Institut Teknologi Sepuluh November (ITS).

Duffield, Colin. (2003). International Project Management, UI.

Ervianto, W. (2005). Manajemen Proyek Konstruksi (Edisi Revisi), Yogyakarta: Andi.

Fayek, Aminah., Knight, Karla. (2002). Use of Fuzzy Logic for Predicting Design Cost Overruns on Building Projects, ASCE Journal of Construction Engineering and Management.

Godfrey, P., Halcrow, W. S., & Partners, L. (1996). Control of Risk A Guide to Systematic Management of Risk from Construction. Westminster, London: Construction Industry Research and Information Association (CIRIA).

Kerzner, Harold. (2006). Project Management: A system Approach to Planning, Schedulling, and Controlling, John and Wiley, Inc. Ninth Edition, New Jersey.

Mulyawan, Setia. (2015). Manajemen Risiko, Bandung: CV Pustaka Setia.

PMI (Project Management Institute, Inc). (2004). A Guide To The Project Management Body Of Knowledge (PMBOK), 3rd edition, Newtown Square, Pennsylvania, USA.

Rantung, B.T., Dundu, A.K.T., Tarore, Huibert. (2018). Pengelolaan Risiko pada Pekerjaan Pembangunan Jalan Tol Manado-Bitung (Sta. 9+700 s/d Sta. 11+700), Jurnal Sipil Statik Vol.6 No.5 Mei 2018 (353-360) ISSN: 2337-6732, Program Studi Teknik Sipil Pascasarjana Unsrat, Manado.

Riduwan. (2009). Metoda dan Teknik Penyusunan Tesis, Bandung : Alfabeta.

Rosdianto, M.A. (2017). Analisa Risiko Keterlambatan Proyek Pembangunan Apartemen di Apartemen Taman Melati Surabaya, Magister Manajemen Teknologi, Institut Teknologi Sepuluh November, Surabaya.

Rumimper, R.R., Sompie, B.F., Sumajouw, M.D.J. (2015). Analisis Risiko pada Proyek Konstruksi Perumahan di Kabupaten Minahasa Utara, Jurnal Ilmiah Media Engineering Vol.5 No.2, September 2015 (381-389) ISSN: 2087-9334, Program Studi Teknik Sipil Pascasarjana Unsrat, Manado.

Rusim, D.A., Parung, Herman., Latif, R.U., Tjaronge, Wihardi. (2018). Analisis Risiko terhadap Waktu Pelaksanaan pada Pembangunan Infrastruktur Jalan di Jayapura, Prosiding Seminar Nasional Teknik Sipil 2018 ISSN: 2459-9727, Fakultas Teknik Universitas Muhammadiyah Surakarta.

Senduk, Novatus., Willar, Debby., Manoppo, F.J. (2016). Pemodelan Pengelolaan Risiko Proyek pada Perusahaan Penyedia Jasa Konstruksi Skala Kecil (Studi Kasus Kontraktor di Manado), Jurnal Ilmiah Media Engineering Vol.6 No.2, Mei 2016 (498-507) ISSN: 2087-9334, Program Studi Teknik Sipil Pascasarjana Unsrat, Manado.

Sugiyono. (2009). Metode Penelitian Bisnis, Bandung: Alfabeta.

Sukaarta, I.W., Sompie, B.F., Tarore, H. (2012). Analisis Risiko Proyek Pembangunan Dermaga Study Kasus Dermaga Pehe di Kecamatan Siau Barat Kabupaten Kepulauan Sitaro, Jurnal Ilmiah MEDIA ENGINEERING Vol. 2, No. 4, November 2012 ISSN 2087-9334 (257-266), Prodi Teknik Sipil Pascasarjana Unsrat, Manado.

Tjakra, Jermias., Sangari, Freyke. (2011). Analisis Risiko pada Proyek Konstruksi Perumahan di Kota Manado, Jurnal Ilmiah Media Engineering Vol.1 No.1, Maret 2011 ISSN 2087-9334, Program Studi Teknik Sipil Pascasarjana Unsrat, Manado.

Tumimomor, J.E.E., Manalip, H., Mandagi, R.J.M. (2014). Analisis Risiko pada Konstruksi Jembatan di Sulawesi Utara, Sabua Vol.6, No.2: 235-241, Agustus 2014 ISSN 2085-7020, Program Studi Teknik Sipil Pascasarjana Unsrat, Manado.

Williams, T.M. (1993). Risk Management Infrastructure, International Jurnal of Project Management.




DOI: https://doi.org/10.30601/jtsu.v7i2.1989

Refbacks

  • There are currently no refbacks.


Copyright (c) 2021 Julianda Astari Kawulusan

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Teknik Sipil Unaya


Creative Commons License

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

© Jurnal Teknik Sipil Unaya : Published by Center for Research and Community Service (LPPM) University of Abulyatama, Aceh, Indonesia. 2019